Restoring the Library – Part 2

Be sure to check out part 1 of the library restoration.

The library has seen significant progress since removing the second kitchen this summer. Here is where we left off for reference:

After removing the second kitchen used by the bed and breakfast.

The first order of business, remove the layers of flooring, and expose the original wood:

To the left, evidence of a fireplace. The house originally had six marble fireplaces, only one original remain in the dining room.

The original wood underneath is in much better condition than we expected. There are three square openings for vents and various holes for plumbing the kitchen that will need to be plugged.

Next, we move on to the casing and trim around the historic window. This project was an undertaking, and we were fortunate to be working with a talented carpenter that was excited to take on the effort. Here is a picture of what we started with:

A little bit of everything was needed, from casing to filling holes, baseboard moulding, and intricate trim.

From casing to trim, there was a lot to put back in order:

Upon careful inspection, we know there was originally a doorway walled off leading from the library to the bathroom connected to the men’s parlor. We decided to give it a go and open it up:

To our surprise, the door jam was left in great shape. We also found the original door in the basement; perfect match!

Matt Heaney confirming the door fits! Nearly all of the doors and windows in the house are different sizes.
A new perspective emerges seeing the beautiful library window from the bathroom.
The library only had one entrance and always felt a bit disconnected from the rest of the house. Space flows much better with the door-way opened up.

What’s next? The final effort of this room is waiting on the following:

  • When we removed the walled-off doorway, we introduced a new problem: We don’t have enough original casing moulding to surround the door. We had the moulding custom milled in St. Louis. It’s now complete and ready for pick up.
  • The library originally had a marble fireplace. We have a hand-carved marble fireplace mantel surround coming in from New York scheduled to arrive this week. It took Alexandria months to make a decision, and it’s beautiful!
  • The transom above the door we opened up was originally stained glass, and we are working on having a replacement reproduced. It’s an interesting architectural element given that the transom “goes nowhere” but is there for consistency. We found that power was run to light the transom.

While our primary focus for 2020 has been on the exterior, we are excited about the progress of restoring our first room. We’re planning on posting updates on the victorian porch soon, so keep an eye out!

Thank you for reading,

Michael and Alexandria Morgan

3 replies on “Restoring the Library – Part 2”

I appreciate you guys taking the time to get quality products and do quality work. So many times I see renos on projects like this that is just butchered and it breaks my heart.

you have done an outstanding job on the work you have done your great grandfather would have been very proud those are things he loved to do GOD bless you and your family for this new year love granny

Leave a Reply

Your email address will not be published. Required fields are marked *